When the soil report says the first twenty feet cannot carry the load, the foundation goes deeper. Deep foundations take a heavy column, tank or machine load past weak, wet, contaminated or frost-affected soil and into ground that holds. The choice of system, driven, helical, micropile or drilled, decides cost, schedule and risk long before a rig shows up.

We build deep foundation packages for heavy industrial plants, shops, process buildings and heavy equipment in Casper and Natrona County. We work from the geotechnical report and the structural engineer's design, and we help owners compare systems on the things that matter in this market: groundwater, rock, contamination, vibration near operating units and access for a rig.

Our drilled pier work is its own discipline, covered separately. This page is about picking the right deep system and building it safely.

Ground conditions that push foundations down

Casper sits where the North Platte meets the foothills. Alluvium near the river holds groundwater, and bedrock and rock-bearing formations sit under the benches. In the town of Evansville, a Superfund site at the Mystery Bridge and US Highway 20 involves groundwater contamination believed to come from former industrial operations. Driving a pile or drilling a shaft there brings questions about what comes up with the spoil and what flows down the hole.

Casper Mountain rises to 8,130 feet, about 3,000 feet above the city, with an anticline and a fault line on its north side. Farther west on US 20/26, the 320 acre scarp at Hell's Half Acre exposes Wind River Formation rock with deep ravines and eroded earth. The lesson is simple: geology changes quickly across short distances here, and a boring log on one corner does not describe the next.

Choosing among driven, helical, micro and drilled

Driven steel piles are fast and give a direct field check of capacity, but they make noise and vibration, and they need open overhead. Helical piers screw in with little vibration and suit lighter loads, tie-downs and tight sites. Micropiles are small-diameter, high-capacity elements that fit in low headroom and difficult access, including inside existing buildings. Drilled shafts carry the largest loads and pass through varied soil, but they generate spoil and need casing or slurry in wet ground.

The decision follows five questions. What is the load and is it uplift or lateral too? How deep is competent soil or rock? Where is the water? What is the neighbor doing, a running unit or a quiet shop? How is the rig getting in? We help the owner and engineer compare cost, schedule and risk, and we can price more than one option so the choice is on paper, not on instinct.

Test first, then production

We build deep foundations in the order that protects the owner. First comes a test element, a load test on a pile, pier or shaft to confirm capacity and installation records. Then production installation follows the same method. Each element gets a log: depth, torque or driving resistance, concrete volume and any variance. The logs go to the engineer in real time, so a bad pile is caught on the day it is placed.

Site layout and sequence are part of the plan. We lay out piers by survey, mark utilities, and set the rig on a stable working pad built from compacted base. Spoil and drilling fluids are handled to the owner's environmental plan. After installation, we cut off, cap and tie elements into the foundation or equipment pad, and we protect exposed rebar and steel from weather.

Design criteria and plan review

Wyoming has no single statewide building code, and the International Code Council notes that local governments adopt and enforce their own. The City of Casper lists the 2024 International Codes as adopted, with amendments in Title 15. Outside the city, the county or town sets its own adoption, so we verify the edition with the building department before design.

City commercial permits often require engineered drawings and plan review of structural calculations and reports. Deep foundation designs need a geotechnical report, pile or pier capacity calculations and a testing plan. Design snow, wind and frost values are set locally. For Casper, the published criteria list a three foot frost line and severe weathering, which affects cap and grade beam depth and detailing.

What changes the price

Depth and count drive cost. So do access, groundwater, contamination and mobilization. A rig that must travel far or work on soft ground adds cost. Casing, slurry, rock sockets and obstructions add risk. Test programs add time but protect the whole job.

We recommend early borings and, when ground is uncertain, a small test program before final pricing. A change order on the third day of drilling costs more than a boring on day one. Heavy panels on tilt-wall sites sometimes need deep elements at corners and openings. We provide unit prices for extra depth and unforeseen rock, so the owner knows the exposure before the first pile goes in.

Rigs, spoil and buried lines

Deep foundation rigs are tall, heavy and powerful. We establish an exclusion zone around the rig, use spotters, and control the swing radius. Overhead lines are measured and marked, and the rig does not move near them without a signal person. We also manage noise and vibration near running equipment, with monitoring if the owner requires it.

Underground work calls for locates and potholing before drilling or driving. On sites with a contamination history, workers wear the required protection and spoil follows the management plan. The permit to work lists the hazards, and every worker attends the orientation. A pile that is a few feet off is a design problem. A person hurt is a real problem.

Send the soil report and the loads

Share the geotechnical report, the structural loads and the site access. We will compare systems, price the options and plan the test program.

Common Questions

How do I know if I need deep foundations?

The geotechnical report tells you. Weak, loose or wet soil near the surface, heavy concentrated loads, uplift or lateral forces, or contaminated fill are the usual triggers. If the report recommends deep elements, get pricing on more than one system.

Are helical piers strong enough for industrial loads?

For lighter structures, tie-downs and some equipment pads, yes. Heavy columns and large tanks often call for driven piles, micropiles or drilled shafts. The engineer sets capacity from the soil and a load test.

What happens if we hit rock or an obstruction?

We stop and notify the engineer. Options include pre-drilling, changing element type or relocating. Unit pricing for extra depth and rock makes the cost predictable.

Can you install piles near running equipment?

Yes, with a low-vibration method such as helical piers, drilled shafts or micropiles, and with vibration monitoring if required. We coordinate with the unit operator through the permit to work.

Do you handle spoil from contaminated ground?

We follow the owner's soil management plan, including sampling, segregation, disposal and worker protection. The plan should be in place before drilling begins.

Next step: Ready to talk about your project?

ServicesBuilding TypesIndustriesService AreasAboutContactRequest a Project Review307-355-4746